South Pars 17&18, 19, 20&21
As the administration of President Hassan Rouhani approaches the end of its term in office, promises of development of South Pars gas field are coming true one after another.
Phases 17&18, 19 and 20&21 have finally become operational, adding more than 150 mcm/d to the country's gas production capacity.
SP 17&18
Date of Signature of Contract: 2006
Date of Operation: 2016
Production Goals:
56.6 mcm/d of sour gas
75,000 b/d of gas condensate
2,740 tons a day of LPG
2,740 tons a day of ethane
400 tons a day of sulfur
Offshore Installations:
4 offshore platforms, 44 wells (105 kilometers off Assaluyeh), two 105-kilometer offshore pipelines, two 105-kilometer glycol transmission pipelines
Onshore Installations:
Treatment facility, four condensate storage tanks, LPG storage tanks
Contractors:
Iran's Industrial and Renovation Organization (IDRO)
Iranian Offshore Engineering and Construction Company (IOEC)
National Iranian Drilling Company (NIDC)
Oil Industries Engineering and Construction Company (OIEC)
Dana Energy Company
Iran Shipbuilding & Offshore Industries Complex Co (ISOICO)
ore Information:
Phases 17&18 of South Pars have generated more than $2.35 billion in revenue since 2014. That is equal 47 tons of gold.
For each phase, 80 kilometers of cable has been installed. That is equal the distance between the cities of Tehran and Qazvin.
The daily production from these phases equals two billion household gas cylinders.
More than 8,000 people per day have been involved in the operation of this phase from beginning to end.
South Pars phase 19
Date of Signature of Contract: 2010
Date of Operation: 2016
Production Goals:
56.6 mcm/d of sour gas
75,000 b/d of gas condensate
2,740 tons a day of LPG
2,740 tons a day of ethane
400 tons a day of sulfur
Offshore Installations:
4 offshore platforms, 21 wells (90 kilometers off Kangan), two 90-kilometer offshore pipelines, two 90-kilometer glycol transmission pipelines
Onshore Installations:
Treatment facility, four condensate storage tanks, LPG storage tanks
Contractors:
Petropars
Iranian Offshore Engineering and Construction Company (IOEC)
Oil Industries Engineering and Construction Company (OIEC)
More Information:
Phase 19 of South Pars has generated more than $800 million in revenue since March 2016. That is equal 25 tons of gold.
For each phase, 80 kilometers of cable has been installed. That is equal the distance between the cities of Tehran and Qazvin.
The daily production from these phases equals two billion household gas cylinders.
More than 11,000 people per day have been involved in the operation of this phase from beginning to end.
Five million tons of earth removal, five million tons of earth pouring
South Pars phases 19&20
Date of Signature of Contract: 2010
Date of Operation: 2016
Production Goals:
56.6 mcm/d of sour gas
75,000 b/d of gas condensate
2,740 tons a day of LPG
2,740 tons a day of ethane
400 tons a day of sulfur
Offshore Installations:
2 offshore platforms, 22 wells (105 kilometers off Assaluyeh), two 105-kilometer offshore pipelines for gas transmission, two 105-kilometer glycol transmission pipelines
Onshore Installations:
Treatment facility, four condensate storage tanks, LPG storage tanks
Contractors:
Iranian Offshore Engineering and Construction Company (IOEC)
Oil Industries Engineering and Construction Company (OIEC)
More Information:
Phases 20&21 of South Pars have generated more than $200 million in revenue since March 2016. That is equal 5 tons of gold.
For each phase, 80 kilometers of cable has been installed. That is equal to the distance between the cities of Tehran and Qazvin.
The daily production from these phases equals two billion household gas cylinders.
More than 10,000 people per day have been involved in the operation of this phase from beginning to end.